The Programme

Design Phase

Week 0-7
appointment
client brief and specification
detailed design programme and approvals
Tender Phase Week 6-12
prepare documentation
evaluate prices
select suppliers and contractors
Manufacture/procurement Week 8-24
fabricate tower units
fitting-out tower units
procure equipment
install equipment
packing and crating
fabricate and pack VCR module
Site Work Week 28-32
construct foundations
install incoming services to tower
erect cab
erect modules and clad towers and externals
commission towers
Specialist Installation Week 33-38
installation and commissioning

      


The Programme